close

HS2 launches third tunnelling machine in London

A giant 847 tonne Tunnel Boring Machine (TBM) is being used to create a tunnel under the capital that wont be used by trains, but will instead be used to deliver materials and remove spoil from the site where HS2’s Euston twin bored tunnel will be constructed.

Engineers from HS2’s contractor, Skanska Costain STRABAG joint venture (SCS JV), launched the machine from the Atlas Road site in North Acton, from where it will build an 853 metre tunnel to the Old Oak Common Station site.

With a 6.2 metre internal diameter, the tunnel will start five metres below the ground and will reach a depth of 20 metres.

Malcolm Codling, HS2’s Project Client for the London Tunnels, said: “The Atlas Road Logistics Tunnel is key to how we will be constructing the Euston Tunnel between Old Oak Common and HS2’s Euston station.

“The logistics tunnel allows us to take 70,000 lorry journeys off the local roads that would otherwise have been required and will reduce the impact of HS2’s construction on the local community.”

The tunnel drive will be completed in around six months, with the tunnel constructed using 4,264 concrete segments forming 533 tunnel rings. 

The segments, each weighing over 3 tonnes, have been produced by Pacadar in Kent.

The tunnel will be used to transport 8,010 tunnel segment rings to construct the Euston tunnel. 

The segment rings are being manufactured by STRABAG in Hartlepool and will never be transported by public road – utilising rail, and the logistics tunnel - all part of HS2’s commitment to sustainable construction.

A conveyor system will also run through the logistics tunnel, and will connect to an existing conveyor at Atlas Road, taking the London clay being excavated to construct the Euston Tunnel to HS2 London Logistics Hub at Willesden Euro Terminal. 

From there, the spoil will be taken by train for re-use at sites in Kent, Cambridgeshire and Rugby.

The TBM being used to construct the tunnel has been repurposed using components from a TBM, ‘Ellie’, that was previously used on the Crossrail project. ‘Ellie’ dug two sections of the Crossrail tunnels in the Capital – from Limmo Peninsula in Canning Town to Royal Victoria Dock, and between Pudding Mill Lane and Stepney Green – boring a total of 2.23 miles.  

Specialist TBM manufacturer, Herrenknecht, has designed a TBM specifically for HS2’s requirements and has expertly remanufactured components including the shield and the cutting wheel.

James Richardson, Managing Director of Skanska Costain STRABAG JV, said: ”This is our third TBM to launch in London and later this year we will have five machines operating. 

“Four of these will be boring the HS2 tunnels, linking West Ruislip and Old Common. 

“Today’s launch is significant as it is not used for the operational railways, but will create a direct link to between our logistics hub and Old Oak Common, allowing us to transport tunnel segments and spoil without using local roads.”

Following a longstanding tradition of naming TBMs after women, members of the local community have selected the name ‘Lydia’ for the TBM. 

Lydia Gandaa is a former teacher at nearby Old Oak Common Primary School and a founding member of the Bubble & Squeak social enterprise in the area. 

She is an active member of the local community, running after school and holiday clubs at the Old Oak Community Centre.

The TBM was switched on following a naming and blessing ceremony at the Atlas Road site. 

Lydia was at the event to see her name unveiled on the giant machine, alongside pupils from Old Oak Primary School.

Speaking about having the TBM named after her, Lydia said: "I'm delighted to have been invited to come down to the HS2 site and am honoured see the TBM that has been named after me. I am passionate about the local community and thank them for choosing my name for the TBM."

 

If you would like to contact Sarah Walker about this, or any other story, please email sarah@infrastructure-intelligence.com.