close

Changing tack: Crossrail advances beyond tunnelling

London’ £15bn Crossrail project reaches a milestone in May as civils contractors start to hand over tunnels and stations to mechanical and electrical fit-out and systems crews. Antony Oliver discusses the critical plans ahead with technical director Chris Sexton and rail system and commissioning director Siv Bharma.

Every major project learns lessons from those that go before it. Crossrail, Europe’s biggest construction project, is certainly no exception, not least as it begins the complex process of turning tunnels into an operating railway.

It is a critical moment. Speak to anyone involved in a recent major rail project and they talk about the biggest risks to meeting the opening schedule as being centred around getting the track, power signalling and communications systems properly integrated, tested and commissioned on time.

For recent examples, think signalling on the Jubilee Line Extension; think baggage handling at Terminal Five. 

“The strategy that sits above everything here is to not leave all the big risks to the end.” Chris Sexton, Crossrail technical director

Hence the priority right now, three years ahead of the first train service, to ensure that the strategy for testing and commissioning the entire railway ahead of handover to the operator is absolutely worked out and agreed. 

“The way in which you do the testing, commission and handover will drive the decisions that you make during the installation of the systems themselves,” explains project technical director Chris Sexton, underlining the reality that as any project nears completion the challenge of managing the risks escalates. 

“So the strategy that sits above everything here is to not leave all those big risks to the end,” he adds. “So we do everything we possibly can to pull the mitigation as far forward in the programme as possible.”

And that, he says, means ensuring everybody on the project really understands what has to be done now in 2015 to ensure that they are completely ready for handover and first trains running from May 2018.

At the sharp end of this work is rail system and commissioning director Siv Bharma, a veteran of many major rail projects in the capital and beyond. And having the whole systems supply chain on board already, he says, plus MTR Corporation (MTRC) the ultimate operator and maintainer, gives Crossrail a major advantage.

“Our systems specification was written very early which meant we were able to reach out to the supply chain early,” Bharma explains. That means being able to tap into the ideas of experienced systems and mechanical & electrical (MEP) contractors including Costain, Alstom, Knorr-Bremse, Westinghouse, Siemens and train manufacturer Bombardier.

“The best thing that the senior management at Crossrail did here was to mobilise the operator and maintainer very early on – it is very unusual to mobilise them seven of eight years ahead of opening.” Siv Bharma

“We have been working to get the test strategies earlier from the supply chain – getting them to mobilise their key thinking people sooner rather than later,” he adds

The first trains come off Bombardier’s Derby production line in February next year and before that date Crossrail has to get its testing specification coordinated and approved to enable it to book the vital test track in Melton by March. 

In fact, MTRC will start running services from 31 May 2015 between Liverpool Street and Shenfield, taking over stopping services from Abellio Greater Anglia. Initially these will operate with the current rolling stock but will be gradually replaced in 2017 by the new Crossrail trains. 

Testing of the new Crossrail trains will begin in June 2016 ahead of the phase one opening in May 2017 to put this new rolling stock onto the Great Eastern Line out of Liverpool Street. Phased openings will follow in 2018 and 2019 ahead of full opening in December 2019.

“By May we have to notify our sponsors DfT and TfL that we are ready to go [with testing] and we have to give them a detailed plan and share our findings with ORR so that two years ahead of that date the whole of the industry gets mobilised,” he explains. “Agreeing this now means that two years ahead the whole industry knows what your game plan is and so what to expect.”

Bharma also points out the initiatives such as making the test track available as early as possible along with investment to construct a new station operations room jointly with London Underground at Blackfriars – to be ready to start testing systems in the Spring this year – will be important in meeting the programme. 

“The best thing that the senior management at Crossrail did here was to mobilise the operator and maintainer very early on – it is very unusual to mobilise them seven of eight years ahead of opening,” says Bharma. “MTRC’s engagement here is a plus – they have the competences in house to help us decide whether the solutions that we are proposing are the best ones and the ability to be able to question and challenge.”

Also available in Spring will be the so-called “Train zero” – a computer version of the train on which to test all systems and scenarios. The project is also investing in a purpose built integration facility – a detailed lab in which all the supplier software is brought together to be tested and  electronically simulate how real trains will operate.

Bharma has learnt many lessons along the way throughout his career, not least from time spent on challenging projects such at the Jubilee Line Extension project in the 1990s.

“The lessons there were that firstly the level of complexity specified [to use a moving block system] was way ahead of its time, and second the level of systems integration specified was highly advanced – all you needed was one or two suppliers not really getting it for problems to occur,” he explains.

“One of the challenges for us is that as we change over the contractors there are new people doing different things, organised in different way. We are now going to have to start this again with new contractors." Chris Sexton

“For signalling you should use the best three year old technology in the world – something that somebody else has already tried,” he adds. “The software that we will use here is just being commissioned in Copenhagen so there will be the opportunity to actually go and see that software in operation. That means we are less likely to have grief.”

So an enormous amount of thinking is already going on to prepare and plan for these critical operations at the back end of the programme. However, Sexton points out that, while these testing strategies are of course crucial, there is also the small matter of having to first construct everything.

And that means as the tunnelling winds down, from May and June 2015 onwards the MEP and systems contractors must start to mobilise to fit out the stations and install the track, overhead line, ventilation, signalling, power and communication kit.

In fact the first of these contractors, Siemens, starts in the Canary Wharf station in February.

“One of the challenges for us is that as we change over the contractors there are new people doing different things, organised in different way,” explain Sexton. “We have done a huge amount of work with our supply chain in terms of moving the industry’s safety behaviour forward and we are now going to have to start this again with new contractors. Particular in the MEP area, the question is how do we drive in the safety culture into a supply chain that is much more fragmented.”

So Sexton’s first challenge is to complete tunnelling and that is by no means a simple task given that much of the final work is under central London. 

Second is for “the tunnelling community to clear off in a timely manner’ as he puts it, leaving the work areas clear for the MEP and systems contractors to access. 

The third on-going challenge, he says, is to continually manage the integration between the civils, MEP and systems designs, each of which was necessarily carried out separately in phases and now must be knitted together. 

“The lesson from other projects is that getting those interfaces roughly right is not good enough. They have to be exactly right. Here the digital model is a huge help,” he says. “On any project the nearer that you get to the end the risk tends to go up – so whatever you can do to pull those risks back is important.”

If you would like to contact Antony Oliver about this, or any other story, please email antony.oliver@infrastructure-intelligence.com.